A budget that stays live
The budget set at kickoff is tracked across the whole lifecycle rather than standing up in a spreadsheet and going stale by week three.
The engagement is the unit of work and the unit of profit. Everything in Octayne hangs off it.
36 of 37 active projects are on track. One at risk — $408K of project budget off track.
| Client | Proj | On track | At risk |
|---|---|---|---|
| Keystone Clinics | 10 | $1.0M | $408K |
| Meridian Foods | 5 | $2.7M | — |
| HarborPoint Logistics | 7 | $2.1M | — |
| Baker Hughes | 1 | $1.7M | — |
| Gridline Energy Partners | 4 | $1.4M | — |
Spend against hours burned. Above the line is a margin problem before it is a budget problem.
In the product
Structured the way the client bought the work, not the way finance codes it.
Created with the project, or linked to whichever already exists.
Bookings against real capacity, with the plan and the staffing on one record.
Planned against actual by workstream, refreshed as cost lands.
One score per engagement, decomposed into the four things that move it.
Where the current burn rate lands, drawn from week six rather than at close.
Vendor cost hits margin the day it posts.
The same engine grouped by practice area, client or firm.
The budget set at kickoff is tracked across the whole lifecycle rather than standing up in a spreadsheet and going stale by week three.
Burn is measured per workstream, so drift is attributable to a part of the engagement rather than showing up as one bad number at the end.
The plan and the budget it was priced against stay on the engagement, so a scope change shows as a change against what was originally committed rather than as a new normal.
The agentic layer
Margin is decided in the weeks nobody is looking. The agent watches burn against the plan on every engagement and escalates the week the gap opens, not at close.
In week six
Every input to margin is counted as it lands — time, expense and vendor commitment. The forecast at completion has moved off target and the trend is monotonic, not noise. Eight weeks of budget remain to correct it.
Budget burn is running twelve points ahead of hours burned on this workstream alone. The other three are on plan. Vendor cost of $21k is committed but not yet invoiced.
Down one level
Hours against budget, workstream by workstream, with the forecast to completion drawn from the burn rate you are actually running — so a below-target finish is visible in week six rather than at the close.
86% of the budget is consumed against 73% of the work delivered. At the current rate this engagement finishes $63K above its cap — there are six weeks left to change that.
Key insights
Inputs and outputs
The agentic layer
Next step
Bring an engagement that worried you. We will show you where the margin went, and the week Octayne would have told you.